Plans begin for Phase 2 of the GG. Brown Addition

Bookmark and Share

Phase 1 of the G.G. Brown addition is wrapping up as the Emergency Egress is completed. The final steps during Phase 1 include:

  • June 13-14: Temporary walk asphalt placed
  • June 15 & 19: Lean-to installed
  • June 20-21: Temporary lighting installed and area cleaned up
  • June 22: Temporary fence relocated, Phase 1 Egress opened

Phase 2 is scheduled to begin June 23 with the installation of the Earth Retention System (ERS). No additional parking spaces will be lost during Phase 2.